2015 Remedial Law, Q6

A law was passed declaring Mt. Karbungko as a protected area since it as a major watershed. The protected area covered a portion located in Municipality A of the Province I and a portion located in the City of Z of Province II. Maingat is the leader of Samahan ng Tagapag-ingat ng Karbungko (STK), a people’s organization. He learned that a portion of the mountain located in the City of Z of Province II was extremely damaged when it was bulldozed and leveled to the ground, and several trees and plants were cut down and burned by workers of World Pleasure Resorts, Inc. (WPRI) for the construction of a hotel and golf course. Upon inquiry with the project site engineer if they had a permit for the project, Maingat was shown a copy of the Environmental Compliance Certificate (ECC) issued by the DENR-EMB, Regional Director (RD-DENR-EMB). Immediately, Maingat and STK filed a petition for the issuance of a writ of continuing mandamus against RD-DENR-EMB and WPRI with the RTC of Province I, a designated environmental court, as the RD-DENR-EMB negligently issued the ECC to WPRI.
On scrutiny of the petition, the court determined that the area where the alleged actionable neglect or omission subject of the petition took place in the City of Z of Province II, and therefore cognizable by the RTC of Province II. Thus, the court dismissed outright the petition for lack of jurisdiction.
a.) Was the court correct in motu proprio dismissing the petition? (3%)
Assuming that the court did not dismiss the petition, the RD-DENR-EMB in his Comment moved to dismiss the petition on the ground that petitioners failed to appeal the issuance of the ECC and to exhaust administrative remedies provided in the DENR Rules and Regulations.
b.) Should the court dismiss the petition? (3%)

Quick check

Is a trial court authorized to motu proprio dismiss an environmental petition on the ground of improper venue?

Where should a petition for a writ of continuing mandamus be filed under the Rules of Procedure for Environmental Cases?

What is the consequence of failing to appeal the issuance of an ECC to the DENR Secretary before filing a petition for continuing mandamus?

When does the extraordinary remedy of a writ of continuing mandamus lie against an administrative agency officer?

Choices available with full access.

What is the proper administrative remedy to challenge an ECC issued by a DENR-EMB Regional Director?

Choices available with full access.

Unlock the full Remedial Law answers

Learn more about these topics

1. Improper Venue Dismissal
Under Rule 9, Section 1 of the Rules of Court and the Rules of Procedure for Environmental Cases, improper venue is not a jurisdictional ground for the motu proprio dismissal of a petition. Venue in environmental actions is procedural and intended for the convenience of the parties. While a petition for a writ of continuing mandamus should be filed in the Regional Trial Court exercising territorial jurisdiction over the area where the actionable neglect took place, courts cannot dismiss an action on the ground of improper venue unless the respondent formally raises venue as an affirmative defense.

2. Administrative Remedies Exhaustion
Under the doctrine of exhaustion of administrative remedies, a party seeking judicial relief against an administrative decision or action must first exhaust all available administrative remedies before resorting to court action. Under the DENR Rules and Regulations governing Environmental Compliance Certificates (ECCs), an aggrieved party must appeal the issuance of an ECC by a Regional Director to the DENR Secretary. Filing a petition for continuing mandamus without pursuing an administrative appeal violates this doctrine, rendering the petition premature and subject to dismissal.

3. Continuing Mandamus Scope
A writ of continuing mandamus is a special civil action available under the Rules of Procedure for Environmental Cases to compel a government agency or officer to perform an act specifically enjoined by law as a duty. However, the extraordinary writ lies only when there is no other plain, speedy, and adequate remedy in the ordinary course of law. Where an administrative appeal mechanism is provided by agency regulations to review and set aside an allegedly negligent ECC, judicial intervention via continuing mandamus is unavailable until administrative remedies are fully exhausted.

About these questions and answers
The questions reproduced here are the official texts of the Philippine Bar Examinations, published by the Supreme Court. They are reproduced for study purposes.The suggested answers are the author’s own.

They are not official answers, have no connection with the Supreme Court, the Office of the Bar Confidant, or any bar review institution, and are not endorsed by any of them. Official answer keys, where released, should be preferred over anything here.Nothing on this page is legal advice, and reading it creates no lawyer-client relationship. Do not rely on any suggested answer in an actual legal matter. Consult counsel on your own facts.Suggested answers reflect the law and jurisprudence the author considers applicable as of the date shown.

Where a question comes from an earlier examination, the suggested answer applies the law as it now stands, which may differ from the law in force when the question was given, and may therefore differ from what would have been the correct answer at that time. Where the difference is material, the answer notes it.The practice scoring feature measures wording overlap with the suggested answer. It is not a grade, carries no official weight, and says nothing about whether your reasoning is sound.Errors are possible. If you find one, please tell me and I will correct it.Last reviewed: October 2026